How much concrete to order for a slab, footing or post, in yards, m³ and bags.

Your details

ft
ft
in

For several identical footings or posts.

%

5% to 10% is typical.

$

Ask your local supplier; delivery fees are extra.

$

You need about 1.25 m³ (1.63 cubic yards) of concrete, or 88 bags of 30 kg mix.

Concrete to order

1.63

cubic yards · 1.25 m³

Bags of 30 kg mix

88

44 cubic feet

Ready-mix cost

$324

at $260 per m³

Bagged cost

$748

at $8.50 per bag

What this means for you

  • Note: Order 1.25 m³ (1.63 cubic yards), including 10% extra for spillage, uneven ground and form flex.
  • Note: That's 88 bags of 30 kg mix, a lot of hand mixing. Ready-mix delivery is usually faster and gives a stronger, more even pour.
  • Good news: At your prices, ready-mix is cheaper: ready-mix about $324, bags about $748, before delivery fees.
Ready-mix vs bags
  • Cost

Ready-mix prices often add delivery and short-load fees; check with your local supplier.

Ready-mix cost at other prices
  • Ready-mix cost

Prices vary by city, season and order size. Use this to compare quotes.

Concrete needed at other thicknesses
  • Cubic yards

Same length and width, including your waste allowance.

Compare scenarios

Save your current numbers, change one of your inputs, and save again to see them side by side.

Full report

Get your full report: charts, scenarios and an action plan, plus Excel

Your order list for ready-mix or bags, costs at other thicknesses, a pour-day checklist and questions to ask your supplier.

Was this calculator helpful?

Concrete to order

1.63

How to calculate concrete

Concrete is ordered by volume. Multiply length × width × thickness, using the same unit for all three, then add 5% to 10% for waste. For a round post hole or column, use π × radius² × depth.

  • Imperial: cubic feet ÷ 27 = cubic yards. A 12 × 10 ft patio at 4 in is 40 ft³, or about 1.5 yd³.
  • Metric: a 3.6 × 3 m slab at 10 cm is 1.08 m³. Add 10% and order about 1.2 m³.

Worked example

A 12 × 10 ft patio, 4 in thick, with 10% extra needs about 1.25 m³ (1.63 cubic yards). That’s about 88 bags of 30 kg mix, so ready-mix delivery is the easier choice.

Typical thickness

ProjectTypical thickness
Walkway, patio, shed pad4 in (10 cm)
Driveway, garage floor5 to 6 in (12.5 to 15 cm)
FootingsPer your design and local code

Ready-mix or bags?

Bags make sense for fence posts and small pads. Above about 1 m³, ready-mix is faster, more consistent and often cheaper, even with a delivery fee. In Canada, ask for air-entrained concrete for outdoor work so it survives freeze-thaw cycles and de-icing salt.

Frequently asked questions

How many bags of concrete do I need for a 10 × 10 slab?

At 4 in thick, a 10 × 10 ft slab is about 0.94 m³ (1.23 yd³). With 10% extra, that's about 74 bags of 30 kg mix.

How much is a yard of concrete in Canada?

Prices vary by city and season. Many suppliers charge roughly $200 to $300 per m³ (about $150 to $230 per cubic yard) plus delivery. Get a local quote.

How much extra concrete should I order?

Add 5% to 10%. Running short mid-pour causes a weak cold joint, so it's better to have a little left over.

How long before I can walk or drive on new concrete?

Usually about a day for foot traffic and about a week for cars, with full strength at around 28 days. Cold weather slows curing.